As a part of Burwood Council's Capital Works Roads Program for 2022-23, Council’s delivery team will be undertaking road rehabilitation works on the following streets:
Clarendon Place, Burwood
The project commenced on 8 May 2023 and completion will occur by 17 May 2023, weather permitting. Work will happen during night shifts on Mondays, Tuesdays, and Wednesdays. Work will be carried out between 9:00pm-5:00am, the road will be closed to motorists.
Deane Street
The project commenced on 8 May 2023 and completion will occur by 22 May 2023, weather permitting. Work will be carried out between 7:00am-5:00pm, motorists will have restricted access.
Webb St, Croydon
The project is scheduled to commence in late May 2023 and completion early June 2023, weather permitting. Work will be carried out between 7:00am-5:00pm, motorists will have restricted access.
Morris Lane, Burwood
The project is scheduled to commence on mid June 2023 and completion late June 2023, weather permitting. Work will be carried out between 7:00am-5:00pm, motorists will have restricted access.
Park Avenue, Burwood
The project is scheduled to commence in early June 2023 and completion mid June 2023, weather permitting. Work will be carried out between 7:00am-5:00pm, motorists will have restricted access.